Project Introduction: The total installed capacity of this project is 1 million kilowatts, equipped with 160 wind turbine units, each with a capacity of 62.5 kilowatts. Two new 220-kilovolt step-up substations have been constructed, and the project will connect via a single-circuit 220-kilovolt transmission line to the 500-kilovolt collection substation of the 1.38-million-kilowatt ecological governance wind power base in Keerqin District, Tongliao City. After the project goes into operation, it will save approximately 969,600 tons of standard coal annually, yielding significant economic, environmental, and social benefits. It will also effectively improve the power supply structure of the local grid and contribute to local ecological conservation and green development.